This is the first in a series that will follow the renovation of Stokley Field at the Central Region Little League Headquarters on the east side of Indianapolis. J&D Turf is heading up the field renovation. The renovation will consist of the following:
1. Removal of existing vegetation and brick dust infield
2. Laser grading of rootzone
3. Installation of new irrigation system
4. Installation of new fencing
5. Installation of a new perimeter drain behind the outfield fence
6. New Kentucky bluegrass sod
7. New infield mix - Dura Edge Classic from Natural Sand Company
8. New Dura Traxx warning track material for Natural Sand Company
The project will be completed by the end of May. The tournament begins in early August.
Here are two photos taken before construction begins. As you can see, the existing turf was sprayed with Glyphosate to ensure complete kill of the old fescue/annual bluegrass turf.
To learn more about the Central Region Little League Headquarters, click HERE
To learn more about Stokley Field, click HERE
Go the j-dturf.com to learn more about J&D Turf
Play on!
--Jamie
Saturday, April 30, 2011
Central Region Little League - Stokely Field - Let the Renovation Begin
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment