Following the drainage install, it was time to grass and grow in the playing surface. A granular Ronstar application was made prior to Northbridge bermudagrass sprig installation by Grassmaster Turf Farm on June 7, 2017. Opening Day was approx 8 weeks away.
Following sprig installation, a heavy watering cycle took
place for 14 days. After the sprigs began
to green up the surface was placed on an aggressive grow in program consisting
of Foliar-Pak Grow In and Ammonium Sulfate.
Weekly applications were made and the field was mowed 3 times per week
at a 7/8 inch cutting height.
June 7, 2017 at Sprigging
June 17, 2017
June 20, 2017
July 5, 2017
August 8, 2017
The playing surface as of August 8, 2017 was perfect. The next question was “How well will it play?”